Brazos County Commissioners Approve A Fourth Change To The Design Contract Of Administration Building Renovations

Brazos County administration building, May 29 2023.
Brazos County administration building, May 29 2023.

For the fourth time, Brazos County commissioners amend the contract to design remodeling and repairs at the administration building.

Adding about $255,000 dollars to the design contract brings the total design cost to $1.6 million dollars. That is nearly double the original design contract of $867,000 dollars.

The commission’s project director, Trevor Lansdown, says repairing the building “envelope”, the area between interior walls and the exterior brick, has nearly doubled the entire project cost to an estimated $17 million dollars.

The original design for renovating the county’s administration building included creating more office space by doing among other things, adding a second floor to the former church sanctuary.

Click HERE to read and download original plans for remodeling the Brazos County administration building.

Click HERE to read and download the assessment report of the Brazos County administration building “envelope”, the area between interior walls and the exterior brick.

Click HERE to read and download the fourth amendment to the design contract that was approved during the May 28, 2024 Brazos County commission meeting.

Click HERE to read and download the second and third amendments to the design contract that was previously approved by Brazos County commissioners.

Click HERE to read and download the first amendment to the design contract that were previously approved by Brazos County commissioners.

Click HERE to read and download the original design contract that was previously approved by Brazos County commissioners.

Click below to hear comments from the May 28, 2024 Brazos County commission meeting.

 