The landscape on the west side of Bryan will be changing.
That’s after the city council Tuesday night approved without comment a design contract for a new water tower next to the Chick Lane curve between Leonard Road and Villa Maria.
Public works director Jayson Barfknecht told the council in July that the design process and the build can start during this fiscal year.
The design process is expected to take eight months and construction of the two million gallon tower is expected to take 15 months.
During Barfknecht’s report in July, he also talked about another tower being built “outside of the window of my career with the city” north of downtown where two tanks currently sit along Tabor between 16th and 18th.