Exterior construction has been completed at Blinn College’s new Bryan campus administration and student services building.

That was part of chancellor Mary Hensley’s update during the August board of trustees meeting.

Site utilities are almost complete, and underway are interior drywall ceilings, wall priming and painting, tile installation, and the mechanical/electrical/plumbing rough-ins.

Excavation and grading is underway for the building’s monument sign and intramural field.

Hensley also noted her favorite part of the project is completed. That is the installation of the college’s logo inside the building’s tower.

Completion is still expected in February and the cost will be under the $31 million dollar budget.