Construction Progresses On Blinn College’s New Bryan Campus Administration And Student Services Building

Photo taken April 3, 2024 of the Blinn College Bryan campus administration and student services building and in the foreground, the new Nash Street extension.
Photo taken April 3, 2024 of the Blinn College Bryan campus administration and student services building and in the foreground, the new Nash Street extension.

Blinn College trustees hear that construction continues on schedule at the new Bryan campus administration and student services building.

Chancellor Mary Hensley said all the steel is in place, the paving for the roadway and parking lot is nearing completion, traffic signals have been moved at Villa Maria and Nash, and permanent power has been installed.

The $31 million dollar project is supposed to be completed in February 2025.

Click below to hear comments from Mary Hensley during the April 2, 2024 Blinn College trustees meeting.

 