The Monday after Texas A&M graduation weekend, the new interchange under construction near Easterwood Airport will close for nearly one and a half weeks.
The TxDOT district office in Bryan reports thru traffic will continue on FM 2818/Harvey Mitchell Parkway.
But traffic on FM 60/Raymond Stotzer Parkway will be closed from Monday, May 13 at 9 a.m. through Wednesday, May 22.
This closure also includes all interchange ramps.
This is the last step to complete the $14 million dollar diverging diamond interchange, which began in March 2017.
This closure will allow final surfacing and pavement markings, and adjust roadway grades.
Easterwood Airport will be accessible by using F&B Road and Turkey Creek Road.