The Texas department of transportation (TxDOT) Bryan district office announces the start of widening the Highway 105 portion of the “Aggie Expressway” east of Navasota.
TxDOT social media the widening will add turn lanes at selected intersections along 105 between Highway 6 and near the FM 362 intersection.
Completion of this six mile project is expected in August 2026, weather permitting.
The TxDOT project website says widening 105 to four lanes is currently planned to start in 2029. In addition to a four lane divided highway, there would be interchanges at 105 and Highway 6 and an overpass at 105 and FM 362/Grimes County road 412.