Building a 950 foot long boardwalk over Bryan’s Midtown Park Lake is on hold. That’s after the Bryan city council rejected two bids during April’s regular meeting for being too expensive. The city’s cost estimate was $2.7 million dollars. The lesser of the two bids was almost $3.3 three million.
The Bryan council during its April regular meeting awarded a contract to replace playground equipment at Bonham and Tanglewood Parks. Background information given to the council says replacement parts are no longer available for the Bonham play structures, which were built in 2002. And Tanglewood’s new equipment replaces what was built in 2006. The $465,000 dollar purchase was endorsed by Bryan’s park and recreation advisory committee.
Click below to hear comments from the April 9, 2024 Bryan city council meeting.